Project Status: IN-SERVICE
Strategic Purpose: Cooperative Principles
Project Contact: Brandon Gustafson
Related Resources: Map
Tamarack Substation Tap Line
Dairyland Power Cooperative is building a one-mile, double-circuited 69,000-volt transmission line from an interconnection point on Dairyland's existing Centerville-to-Independence transmission line. The purpose of the transmission line is to deliver electricity to Riverland Energy Cooperative's new Tamarack Distribution Substation, which will be located on Trowbridge Lane in Trempealeau County, Wis. The new transmission line and substation will increase local distribution capacity and improve system reliability for Riverland Energy cooperative members in this service territory.
Project At A Glance |
|
---|---|
County where facilities may be placed | Trempealeau County (Wis.) |
Distribution Cooperative Service Territory |
|
Line length | 1 mile |
Voltage | 69 kV |
Estimated project cost | |
End points | Dairyland's existing 69 kV transmission line to Riverland Energy's Tamarack distribution substation |
69 kV Transmission Line
Schedule |
|
---|---|
(all dates are anticipated and subject to change) |
|
Right-of-way acquisition | December 2022 |
Start of construction (right-of-way clearing) | February 2023 |
Foundations, structures, line construction | May 2023 |
Target in-service date | August 2023 |